Our offshore experience
From wind farms to offshore platforms and subsea connections, our projects span the Middle East, Europe and Asia.
Latest project

Fengmiao 1 offshore wind farm
TaiwanPeak WindEPCI CDWE
- Jacket foundations
- 33
- Offshore substation
- 1
- Year
- 2026
Pile grouting for 33 jacket foundations and one offshore substation.
Major projects
A selection of ULO’s major projects. Open a row for the full scope, the figures and, where ULO recorded one, how long it took.
14 projects
Offshore wind
Grouting for wind turbine foundations and offshore substations.
14Fengmiao 1 offshore wind farmTaiwan · Peak Wind · EPCI CDWE33 jackets
- Scope
- Pile grouting for 33 jacket foundations and one offshore substation.
- Delivered
- 33jacket foundations1offshore substation
- Timeline
- 2026
Hai Long offshore wind farmTaiwan · Northland Power · Mitsui · Gentari · EPCI CDWE73 foundations
- Scope
- Grouted connections for 73 jacket-foundation turbines in the Taiwan Strait.
- Delivered
- 73turbine foundations1,022MWcapacity2offshore substations
- Timeline
- 2024–2025
Saint-Brieuc offshore wind farmFrance · Iberdrola (Ailes Marines) · EPCI Van Oord62 jackets & piles
- Scope
- Grouting of 62 jacket foundations and piles in the Bay of Saint-Brieuc.
- Project details
- Two campaigns: 24 turbine jackets in 2022, then leg-to-pile grouting on 38 more in 2023.
- Delivered
- 62jacket foundations & piles496MWcapacity
- Timeline
- 2022–2023
Zhong Neng offshore wind farmTaiwan · CIP · China Steel (CSC) · EPCI CDWE31 turbines
- Scope
- Grouted connections across 31 turbine foundations.
- Delivered
- 31turbines300MWcapacity
- Timeline
- 2023
Moray West offshore wind farmUnited Kingdom · Ocean Winds (EDPR · ENGIE) · EPCI Boskalis2 substation platforms
- Scope
- Pile grouting for two offshore substation platforms.
- Timeline
- 2023
Changfang & Xidao (CFXD)Taiwan · CIP · COP · EPCI CDWE52 turbines
- Scope
- Grouted connections across 52 turbine foundations.
- Project details
- Pre-piled turbine jacket foundations with more than 150 legs and piles across multiple three-legged foundations, all grouted inside a single 104-day window.
- Delivered
- 52turbines600MWcapacity
- Timeline
- 104 days · Q2–Q3 2023
Baltic Eagle offshore wind farmGermany · Baltic Eagle GmbH · EPCI Heerema1 substation
- Scope
- Pile grouting for the offshore substation.
- Timeline
- 2022
Hollandse Kust West – Alpha substationNetherlands · TenneT · EPCI DEME1 substation
- Scope
- Pile grouting for the West Alpha offshore substation.
- Timeline
- 2022
Fécamp offshore wind farmFrance · Eolien Maritime France · EPCI DEME (SDI)1 substation
- Scope
- Leg-to-pile grouting and rock-socket grouting for the offshore substation.
- Timeline
- 2022
Hollandse Kust Noord – Beta substationNetherlands · TenneT · EPCI Scaldis · DEME1 substation
- Scope
- Pile grouting for the Beta offshore substation.
- Timeline
- 2021
Hollandse Kust Zuid – Beta substationNetherlands · TenneT · EPCI Heerema1 substation
- Scope
- Pile grouting for the Beta offshore substation.
- Timeline
- 2021
Moray East offshore wind farmUnited Kingdom · Moray Offshore Windfarm (East) Ltd · EPCI DEME100 turbine jackets
- Scope
- Pile grouting for 100 turbine jackets and three offshore substation jackets.
- Delivered
- 100turbine jackets3offshore substation jackets
- Timeline
- 2020
Hornsea 2 offshore wind farmUnited Kingdom · Ørsted · EPCI Heerema2 substation jackets
- Scope
- Pile grouting for the offshore substation and reactive compensation station jackets.
- Timeline
- 2020
Hollandse Kust Zuid – Alpha substationNetherlands · TenneT · EPCI Heerema1 substation
- Scope
- Pile grouting for the Alpha offshore substation.
- Timeline
- 2020